Ports Projects

Port rehabilitation projects, including berths and infrastructure, as well as a breakwater and rubber bumpers

Rehabilitating the fenders for sidewalks (6,7,21,22) in Umm Qasr Port

Status : Completed.

Tender Number and Date: (3/Ports/2010)

Execution Period: 155 days

Beneficiary body: the General Company for Ports of Iraq.

Project Value: 1,416,000,000 IQD

The work shall include the following:

  • Performing the defected steel pillars up to the level of (6,6 m) count(117).
  • Manufacturing new steel pillars of hollow square cut with (36,5×35) dimensions cm and with (20 mm) thickness, count (117).
  • Supplying and installing rubber pieces with the dimensions as per the schemes, count (117).
  • Supplying and installing wood pieces (green hard) with dimensions (15×20) cm with a length of (6,6) m, count (117).
  • Supplying fenders, count (22) and replacing fenders, count (12).
  • Supplying and installing rubber fenders for the pantoon, count (8).
  • Lifting the steel structure, H type with (3) m and (6) m length, count (4).
 

The specialized works to rehabilitate the fenders of the sidewalk no (1) Abdullah creek

Status : Completed.

Tender Number and Date: (15/Ports/2011)

Execution Period: 195 days

Beneficiary body: General company for ports of Iraq.

Project Value: 1,187,000,000 IQD

The work shall include the following:

  • Supplying the material, tools, equipment and manpower to perform the works of removing the rubber fenders above and under the level of sea water, count (54).
  • Performing the works of supplying and installing rubber pieces as per the original model, count (54)
  • Supplying fenders as back-up pieces for the installed pieces, count (26)
  • Removing the damaged steel stairs and manufacturing and installing rubber stairs with the same measures, count (4)
  • Maintaining the damaged concrete layer in the front part of the sidewalk and bridges and the caps of the pillars with an area of (1000 m²)
 

Specialized works of manufacturing and installing rubber fenders and rehabilitation of its steel frame at docks (2,3,4, 11) Zobair creek port.

Status : Completed.

Tender Number and Date: (2/ports/2012)

Execution Period: 195 days

Beneficiary body: General company for ports of Iraq.

Project Value: 898,000,000 IOD

The work shall include the following:

  • Supply of materials and workmen to remove the damaged fenders and metal lic frames and replace with an equable
  • Manufacturing and installing the new metallic frames, quantity
  • Supply and installation of a set of rubber pieces, quantity 29
  • Maintenance of a layer of damaged concrete at the front of the port, dimensions